Recurring Milestones - Progress?

P
Philip Kearney 👤 Member for 24 years 5 months

Thanks for replying!

I have given up hope on these recurring activities! Not gonna use them again as they do no purpose for progress!

Microsoft, take note please!

Yes, my s-curve is generated in excel & it show its worth.

What I have done is, took out the recurring activities as it was giving me grief & replaced it with a number of independent 1 day task but marked as milestones so it can be recorded at whatever % I will deem it at.

A
Anoon Iimos 👤 Member for 19 years 10 months

i suggest you do it in excel, you can put formula and never go wrong (at least in Math).