Critical Path in P5!!
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi
sorry English is not my native language. "Votes against me" was meant as against my opinion, not against my person of course!
Regards from Germany
Dieter
Dieter,
Im sure Im not voting against you. What you said is the same as what Rons understanding I believe.
"They show a different longest path depending on if I schedule the projects independently or as one common project."
Will you send me the screenshots please? (I presumed you knew my email already).
best regards
Hi
Too many votes against me, so I tested with three projects which are linked together. I am very sorry, but I am right.
They show a different longest path depending on if I schedule the projects independently or as one common project. Otherwise it would have been a horror for me because Im using this feature for some years.
If youll send me a private message with your email-address, Ill send you the screenshots.
Regards
Dieter
Ron is basically correct in his "how primavera does sums" analysis.
You can go a long way to circumventing these issues by settin g all the projects in the group to the same "Must Finish by" date
actually No Dieter, im just trying to look at the principle, EPS (Enterprise Project Structure), WBS (Work Breakdown Structure). I believe both must function in the same manner in scheduling terms.
if you look at it from bottom - up: If you schedule the activities (under WBS), it will affect the Project; in the same manner, if you run Projects, it will affect the EPS (But I believe there is no function as this).
Anoon
These are two different views.
Into the EPS you group your projects. Along the hierarchy: Access rights and budget.
Project: Special kind of node: Schedule, Export/Import, Check in/out only for one or more projects indepentent from their location within the EPS; inherits access rights from above EPS
Both within table "PROJ" distinguished by "proj-flag"
WBS: Below project; inherit access rights has own budget as well, no schedule, export....
Was this answer to your question?
Dieter
Dieter,
I agree with Ron. Another thing im not sure is the difference between EPS and WBS: if WBS is the mother of activities and EPS is the mother of projects, are they functioning the same when it comes to scheduling or calculations? or summarizations?
Ronald
It depends from how you establish the schedules. There must be one common start and one comon end for all three projects. Then youll get a longest path. (Until now I didnt find an error.) P6 calculates one directed graph and by this is able to calculate the longest path over more projects. This procedure I have used since Version 3.5 now.
I did not yet test multiple paths.
Dieter
Hi ,
I think I think opening the copies of the 3 projects, at WBS view reassemble all into one happy project and proceed to link and schedule.
Regards
Bukola
From my readings, I believe that P6 calculates the critical path for every schedule individually, even if they are linked to other schedules and the other schedules are currently open. Schedules may finish at different times and each schedule calculates a critical path to that finish point, even if another opened schedule has a later finish time. This must also mean that each schedule has their own longest path, independently calculated from the other linked schedules. This flies in the face of Enterprise Scheduling, but I believe that is how P6 ‘works.’
Hi Dieter,
I believe there is no problem because you know how to do it. But the question here is how to establish the critical path or the longest path within three (3) projects? (is that right?)
What Im trying to emphazise is that some experts here still (I believe) has doubts on how the program produce results, which is very difficult for a not so well versed (like me) to determine if what came out after I press F9, is reliable (granting that P6 is not that old). Anyway, I have lots of works to do right?
best regards,
Anoon
Anoon
We have this situation quite frequently, because due to data exchange with partners, mostly a customer project is divided into more projects. There are different calendars, office, leadtimes, site. But no problem.
The calendar setting is per project, but just as default for new activities.
The default calendar for the database is for the summary lines.
Regards
Dieter
please make sure that your three (3) projects uses the same calendar, im not sure if theres an option to assign specific calendar onto a specific EPS (or is it global?), when you open your EPS, it opens all the projects under it (activities view), if each of your project has say, 5k activities, youll be looking at 15K activity window....very difficult, not to mention if you got constraints, using progress override, wrong logic-links etc....
its really difficult to be a Planner!
Hi
Maybe the reason is your parameter setting:
1. Projects --> Settings --> "Define Critical Activities"
2. "F9" --> Options --> "Define Critical Activities"
Any scheduling computes both critical activities by float aund the longest path(s). In the view Activities filter by "Longest Path" equals "Yes"
BUT: The three projects must be properly linked.
Hope that helps
Dieter
Well yo can test it out but copy all 3 projects into singel project and check if it gives you a correct Critical Path
HTH
ALex
Hi Olubukola,
Thanks for you answer. Actually there are links between three projects, but I can not see the longest path as critical apth!!
Hi,
If there are no interproject relationship between the the 3 projects, u will expect 3 Crtitical paths.
If you can establish links btw them this might solve the problem.
Regards
Bukola