You might have multiple resources assigned to various activities. P3 calculates/adds up the budgeted quantity regardless of their unit. So like if you have 600 cum of concrete and 900 mhr on an activity. P3 will give u a budgeted quantity as 1500.
If you need to make sure that the BQ of mhr and your arthimatic sum is same, run a resource tabular/graphic report on your mhr resource id.