S Curves in P6 - how?

D
Derek Allport 👤 Member for 15 years 7 months

Dear Arnold,

      Please send to me the P6-S-Curve example to

 

derekallport    (at) h o t m a i l . c o m     - without spaces

 

I appreciate your help

B
Behzad Sheikh 👤 Member for 15 years 7 months

Hi Guys,

Load the resources activity by activity, then go to resorce profile and select the resource whose s curve you want to see.Once you click the resource s- curve is dispayed. 

 

very easy..:-)

S
Sankar Vijayan 👤 Member for 15 years 8 months

Dear sir

i am new to p6 .I wanted to give my project manager monthly progress report .I am not assigning any resourses & all.Can u help me how to prepare S curve for this task. it will be helpful if u sent any tutorial regarding this. my email id is

[email protected]

thanking  you

Sankar Vijayan

S
Sankar Vijayan 👤 Member for 15 years 8 months

Dear sir

i am new to p6 .I wanted to give my project manager monthly progress report .I am not assigning any resourses & all.Can u help me how to prepare S curve for this task. it will be helpful if u sent any tutorial regarding this.

thanking  you

Sankar Vijayan

D
dheerendra rao 👤 Member for 17 years 9 months

Dear Sir ,

Please mail me a S curve step proceedure and also late curve .

 

G
GOPALA SRIRAMAN 👤 Member for 20 years 9 months

 

hI Arnold / Any one,

 

Could you please forward me the guidelines  for creating the  S curves  along the templates.

My e mail   [email protected]

 

 

Thanks,

 

Gopala

A
Arnold Puy 👤 Member for 19 years 1 month

Guys,



Sorry for the late reply. Already sent.



Regards,



Arnold

S
Sakandar Hayaat 👤 Member for 16 years 4 months

Hi Arnold,

Its nice that you are helping people in understanding and proper utilization of P6.

Can I also request you to send me manual and how to create histogram in P6.



Regards,



Sikandar

A
Athar Hashmi 👤 Member for 17 years 2 months

Thanx Arnold,

You have done a great job. It’s very nice.

May Allah bless you here and here after!

J
JV Amande 👤 Member for 18 years 3 months





Arnold,



Thanks for the manual. Surely it will help my planning work a lot.



Just additional Question.



regarding my resources histogram.



im just confused with the output.



ex. week-1 (equipment histogram)



the output of average... = to the minimum qty. used

the output of peak = to the maximum qty. used

the total = it sum-up the qty used from

(Day1-Day6)



now, i want to ask which one is the best reference for reporting purposes.



in addition to this, i’m also confused with my reporting, specifically in excel where i tabulate requipment & labor from week-1 up to the last week.



In normal week sequence,

ex. week-1 (Sat.Sun.Mon.Tue.Weds.thurs.)



but my schedule start at Weds., therefore my week-1 only have 2-days (weds.thurs.) and here i already start allocating my resources (Labor& eqpmt)



my question is that, why is it on the LAST-WEEK, i have no more inputs. is this only normal? i think its because of the two days where i start my Week-1.



thank you and hope to hear your response soon.



Sir, can you please send me a P3 manual.





Thanks and More Power.








D
D Artagnan 👤 Member for 17 years 8 months

guys, i just wanna share that i was able to make an excel sheet that automatically generates s-curve and cash flow, it’s fully editable using the feature of pivot reporting. if interested just send me an email. The data, btw, are parsed thru ms access.

J
JV Amande 👤 Member for 18 years 3 months



hi Arnold,



can you also give me copy about Early and Late S-curve application?



what is my source data? is it the manpower? am confused?



thanks..



jV



here is my e-mail address: [email protected]

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts