That sounds like something similar I had faced a couple of years where I had to constantly change the schedule around while trying to monitor progress.
I came up with a solution with the approval of the project manager.
The idea of the baseline appealed to him so I explained to him that with the liklihood of the programme being changed around so much due to outside forces, I would use excel to monitor the changes to baseline in terms of work effort.
Ther first programme that was agreed, I imported the data to excel & set up the baseline no.1 in graph format.
Any changes to the schedule became the working programme so I was monitoring the working programme for progress.
With the baseline in the background, I exported work & actual work into excel to enable me to show the variance between the baseline, working programme & the actual progress in excel format with satisfactory EVM results & a very satisfield project manager!
I want to come back to Aus and work in Shipbuilding....I love the idea of immovable baselines. Unfortunately with a 6000 line schedule our baselines have a habit of changing due to customer/supplier renegotiation, rolling wave planning, risk occurrence, organisational changes, labour rate changes etc. I guess you have similar issues, but less frequently?
Alexandre,
We already have an EVM tool to generate the graphs, its maintaining baseline integrity Im really worried about.
I guess I would export values into MS Access or whatsoever database, in order to mimic P3s "Store period performance" functionnality
Then I would be able to export these data into MS Excel to generate a graph
Or, create a MS Excel worksheet in which you will manually enter the desired data to generate the graph; I did so years ago to create a sophisticated graph from project data
Do not expect MS Project will do anything so wise for you!
I dont do easy questions. ;-) No Im not surprised that MSP deletes the baseline. This is a symptom of MSP. I use a "locked away and separate" contract baseline but our EVM tool requires a rolling baseline to store changes to BCWS information. You could use the baseline information in the current schedule for this purpose, but its fragile and not easy to change resource rates of task baselines. A solution is to use a separate baseline schedule which should mirror the baseline in the current schedule, but which is easier to control. This seems to work quite well, but carries a significant overhead, as you have to maintain an EVM baseline and a tracking baseline (for tracking Gantts etc). I was wondering which method of working is more popular and whether anyone has developed alternative workarounds to the issues discussed above.
Are you surprised to see that deleting a task will also delete its baseline? In MSP, current schedule and its baselines are stored in the same file.
Use a specific baseline for your "locked away and separate" baseline, say the contract, and another one every time you want to save a picture of your project at a certain amount of completion
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
That sounds like something similar I had faced a couple of years where I had to constantly change the schedule around while trying to monitor progress.
I came up with a solution with the approval of the project manager.
The idea of the baseline appealed to him so I explained to him that with the liklihood of the programme being changed around so much due to outside forces, I would use excel to monitor the changes to baseline in terms of work effort.
Ther first programme that was agreed, I imported the data to excel & set up the baseline no.1 in graph format.
Any changes to the schedule became the working programme so I was monitoring the working programme for progress.
With the baseline in the background, I exported work & actual work into excel to enable me to show the variance between the baseline, working programme & the actual progress in excel format with satisfactory EVM results & a very satisfield project manager!
Hey Trevor,
I want to come back to Aus and work in Shipbuilding....I love the idea of immovable baselines. Unfortunately with a 6000 line schedule our baselines have a habit of changing due to customer/supplier renegotiation, rolling wave planning, risk occurrence, organisational changes, labour rate changes etc. I guess you have similar issues, but less frequently?
Alexandre,
We already have an EVM tool to generate the graphs, its maintaining baseline integrity Im really worried about.
Cheers...
Steve
Steve,
I guess I would export values into MS Access or whatsoever database, in order to mimic P3s "Store period performance" functionnality
Then I would be able to export these data into MS Excel to generate a graph
Or, create a MS Excel worksheet in which you will manually enter the desired data to generate the graph; I did so years ago to create a sophisticated graph from project data
Do not expect MS Project will do anything so wise for you!
Alexandre
Baseline means Baseline.
It doesnt change.
Its not supposed to.
There wouldnt be any point in having it if it did change.
If you delete a Task, then that Task no longer exists, so of course its Baseline does not exist.
This is perfectly reasonable to me.
I dont do easy questions. ;-) No Im not surprised that MSP deletes the baseline. This is a symptom of MSP. I use a "locked away and separate" contract baseline but our EVM tool requires a rolling baseline to store changes to BCWS information. You could use the baseline information in the current schedule for this purpose, but its fragile and not easy to change resource rates of task baselines. A solution is to use a separate baseline schedule which should mirror the baseline in the current schedule, but which is easier to control. This seems to work quite well, but carries a significant overhead, as you have to maintain an EVM baseline and a tracking baseline (for tracking Gantts etc). I was wondering which method of working is more popular and whether anyone has developed alternative workarounds to the issues discussed above.
Hello Steve,
Quite complicated, what you want!
Are you surprised to see that deleting a task will also delete its baseline? In MSP, current schedule and its baselines are stored in the same file.
Use a specific baseline for your "locked away and separate" baseline, say the contract, and another one every time you want to save a picture of your project at a certain amount of completion
Alexandre