For me to create any s-curve for any type data, I will always use either the Task Usage View / Resource Usage View. I find it really helpful as we can choose which data to show either cost, resource or work. And what Ill do after that is just simply copy and past into excel and further customize into chart. I hope this will help.
1. Schedule your project from the end date and then export your data
2. Display the Task Usage view, then add the Work, Cost, ... and the Early Start/Finish, Late Start/Finish dates, and copu/paste the data into MS Excel
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Mohammed,
For me to create any s-curve for any type data, I will always use either the Task Usage View / Resource Usage View. I find it really helpful as we can choose which data to show either cost, resource or work. And what Ill do after that is just simply copy and past into excel and further customize into chart. I hope this will help.
m.fakry
Mohammed,
you are right, there is still some work to do to fix the table; a excel macro would help!
Alexandre
Tq Alex,
I have done as your suggestion but I have to arrange the "Work" tabulation MANUALLY. Is that the correct way? Just to confirm..Anyway TQ very much.
Regards
Mohammed,
MS Project is not really efficient to do that!
You could:
1. Schedule your project from the end date and then export your data
2. Display the Task Usage view, then add the Work, Cost, ... and the Early Start/Finish, Late Start/Finish dates, and copu/paste the data into MS Excel
Alexandre