Changing Duration from Hour to Day in P6

Z
Zoltan Palffy 👤 Member for 16 years 11 months

edit users preferences thne Time units Tab 

durations format

choose day

J
Jeanpierre NJEIM 👤 Member for 7 years 8 months

Hi



Concerning  histogram in resource usage profile the Axis "Y" it written  EX: 2.50d,5.0d,... i need to change it into 2h,4h,6h,... 

if anyone can help

Thank you

M
Martin De Beer 👤 Member for 17 years 11 months

Hi Arnold



I actually got the issue resolved thanks.



The problem was the P6.1(contractor) to P5(me) conversion. When using a friend’s P6.1 the duration was changed to days and worked just fine.



Thanks

M
Martin De Beer 👤 Member for 17 years 11 months

Hi Arnold



Normaly you could change the duration by typing i.e 3 days. After changing the duration to days, the activities display duration in days but if you change original duration to 3 it is not 3 days but 3 hours.



I like P6 in some ways but in some ways it SUCKS..



Know P3 well though..

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Martin,



As far as I know, you can only change the hour to day is from user preferences as what you did.



By the way, what do you mean "when you enter durations it is still in hours"?



Arnold

Forum Sponsor

Top Posters

James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts