Successor with Relationship FS (finish to start)Problem
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Youre Welcome. Keep on Planning.
Cheers.
Hi Arnold,
I have a good news for you,I made all you said and it worked
Thanks for your usual useful help.
Abeer
Hi Abeer,
Im sorry.. I forgot to mention that I am using P6. Well, the only way you is to put 1 day Lag for all the activities that the relationship equal to FS and the Finish date of the Predecessor is equal to the start date of its Successor.
You can do this by exporting to excel using Export Type "Activity Relationships" and filter by “Relationship Type equals FS” & “Lag equals 0”. You can easily modify in Excel sheet showing the Star Date and Finish Date of each activities.
Or you can send your programme to me at [email protected] and I will guide you how to do it.
Regards,
Arnold
Hi Arnold,
Sorry to say this it didnt work and kindly note that I use P5 not P6 may be there is a difference in steps.
Thanks for your trials.
Abeer
Hi Abeer,
Go to Edit --> User Preferences --> Date Tab --> Time --> Show Minutes & Select 12 or 24 hour then close. Now, try to check the Finish Date of your Predecessor and modify. Try to observe if you will change the time.
Because P6 Calendars is in hours (half-hour). This is the reason why this sort of situation always happen especially if your predecessor is a Start Milestone.
HTH.
Arnold
Hi Arnold
I appreciate your concern
Kindly note that I did these steps before (but instead of rename calendar I added new calendar)and today I followed your steps and the two ways didnt work I wonder why!!!
Thanks,
Abeer
Hello Abeer,
Try the following steps:
1. Go to Enterprise --> Calendars, select Add and select the 7-day Workweek as your inherent calendar.
2. Rename calendar & select Modify
3. In calendar box, Work hours/day must be 8 hours.
4. In calendar box, select Workweek & if you are in Middle East put 0 in Fri then OK. It depends in your Holidays and Non-working days.
5. Set your new calendar as Default.
6. & assigned this calendar to your activities.
Just try the steps above if it is working with you.
HTH.
Arnold
Hi Arnold,
Thanks for your fast reply.
I checked the mentioned link but I really didnt understand what I must do to get out of this problem
I tried to change hours per day from 8 to 8.5 but it didnt work I must be doing something wrong.
So can you please till me the way as a step to get it or gave me another direction if you please.
Thanks,
Abeer Mohamed Taher
Hi Abeer,
Check this link:
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=49916
Arnold