assign calendars to many activities in one step

H
Hamed Najmzadeh 👤 Member for 9 years 10 months

Dear All

how we can insert new project with different calendar in existing project in primavera?

Sincerely Yours

H.Najmzadeh

S
Syam Mohan 👤 Member for 10 years 2 months

Hi everyone,

                  The Start date and finish date is not matching according to the duration given. calendar assigned is same for all activities. Can anyone tell me the reason for this wrong dates.

R
Riyadh Yahia 👤 Member for 17 years 10 months

Hi Abeer,



To add a calender in one step, try this:



1- Add calender Column from Column (General Option.



2-Add desired Calender to First activity on Top of the Column.



3- Point the arrow on empty Calender Cell at the Bottom of the Calender Column.



4- By using(SHIFT + UP ARROW) OR (SHIFT + MOUSE POINTER) highlight the activities From bottom to Top......upto the assigned calender.



5- As you Reach the Assigned Calendr, make Right click choose Fill Down.



you can use same way to add any item.



best regard



riad

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Abeer,



You can assign calendar for the existing activities using GLOBAL CHANGE.



Calendar = "Select Calendar"



If you wanted to change the selected activities only then you need to filter prior to run Global change.





Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts