thanks Darren. I will check these settings. I posted the whole row.
Hi Varun,
A few of the most likely causes for you to investigate are listed below:
1) Are the default calendar options the same in all the projects? (Tools > Options > Calendar)
2) Are the calendar working times the same? (Tools > Change Working Time)
3) Are the resource Base Calendars the same? (View > Resource Sheet)
4) Are the Task Calendars the same? (In the Gantt View – Insert > Column > Task Calendar)
5) Is the calculation mode set to automatic? (Tools > Options >Calculation)
6) Did you copy the whole row or just the activity names?
Regards,
Darren