Thanks for your reply.
If we define BOQ as Non-Labor and Manhour as Labor resource then while updating progress by units P5 calculates by adding both units as
%completed = actaul (Labour+NonLbour) units/Budgeted(Labor+Nonlabour units)
Budgeted BOQ=4000 Sqft , Mhrs=250
Actual BOQ=2000 Sqft , Mhrs=100
Progress( by units ) calcuted by P5 is
(2000+100)/(2000+250)=49.41%
But actually BOQ is 2000/4000=50%
How can we update progress on BOQ Nonlabour resource units only and planned Labour Manohours units depending on BOQ.I want to update progress by BOQ .
Please advise.
The other way round.
Labour - productive work (especially physical work done for wages)