Resource Management Features in Primavera P3 & P6

A
Arun R 👤 Member for 14 years

Dear All,

                  I what to know is there any internationally accepted standard for work quantity Vs manhour?

For example 50cubic meter concreting needs this much manhour, like that? Please help......I want to know how resourses can be assigned in activities.

A
Alex Wong 👤 Member for 23 years 4 months

Hi All



In terms of resource management, there is 2 main stream (IMHO)

1. Resource Capacity Planning @ portfolio level

2. Resource scheduling @ project level



I implemented in sereval org for both options using P6.



In order to successfully implement resource planning / scheduling, the organisation will need to have the right people and processes, to make the tools become effective. That is the biggest challenges not the tools itself.



If I look at the tools itself, P6 do provide the integration of the project schedule as well as the flexibility.



HTH



Alex

N
Neils Gao 👤 Member for 18 years 3 months

Schedule-Primavera

Cost-Shawtrac(or some others, not sure)

Materials-Marine

we make these three softwares fit together to implement a overall project management in china.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts