namaste
it means that you are using a pirated copy of P3
Peace, hempfully,
smilingshagger
Thanks arnold. I follow your advice and all activities are working well.
But now i am facing other problem in same schedule that, i am try to prepare s- curve through by Graphic report and its Showing " Error in RECMGR - status 2"
Can you advice me how to rectify this issue and i am waiting for your reply
Regrads,
Bailay.
Hi Bailay,
The reason why you cannot modify it is because you do not have access to your current project and was restricted by the owner or user. I guess you are using P3x if so, try the following steps:
1. Close your Current Project including Primavera Window.
2. Go to Start -> Programs -> Primavera and select Netset.
3. Type password "netset".
4. From Primavera Network Administration, Select Option
5. Then Select Change Project Owner.
6. Under the Projects, search the project you wanted to change.
7. After selecting your project, change the Owner to P3 then close and exit.
Regards,
Arnold