the steps you mentioned is a good way, typical way to give weight the major phase of a project. Its either by money or manhours. The only problem with this method is that it is static in nature. To correct this we must schedule the phase of each item using soft and hard constraint in any project management software. In this manner we are able to monitor critical activities which very vital for claims in the future,
Member for
23 years 7 monthsRE: WBS
the steps you mentioned is a good way, typical way to give weight the major phase of a project. Its either by money or manhours. The only problem with this method is that it is static in nature. To correct this we must schedule the phase of each item using soft and hard constraint in any project management software. In this manner we are able to monitor critical activities which very vital for claims in the future,
Regards
E. Montales
Datem Construction