Good Morning all, I am in trouble here and would like to solicit your expertise!
1. I would like to manually enter a percent complete, for the tasks that are accomplished.
2. I would like to print out a historam populating workforce and manpower.
I am new to P6 but desperately needed a job. Any and all help is to be grealy appreciated
It is my understanding that a percent complete cannot be entered if the project has not yet started or finished. When I try to check start and finished then enter 100% complete, it is not recognized because the dates have already passed. Please advise and awaiting anyons help,
My applogies
I am needing ton update the schedule, this needs to reflect the tasks to be 100% complete. Is it possible to do this once the dates have passed, It is my understanding that you cannot update the percent complete if the project has not yet started or finished. I cannot check the start and finished because the dates have passed, What should my next step be?
James,
Please ask these questions in a new topic rather than replying to a discussion that is several years old
Good Morning all, I am in trouble here and would like to solicit your expertise!
1. I would like to manually enter a percent complete, for the tasks that are accomplished.
2. I would like to print out a historam populating workforce and manpower.
I am new to P6 but desperately needed a job. Any and all help is to be grealy appreciated.
Sir,
1.Is that a normal , standard procedure & accurate way of updating according to P6 rule or its just only your assumption according to your experiences?
2.Do we need to check the checkbox in “activity percent complete based on activity steps” on the calculation tabs of project details? What is the effect if un-checked?
3.Do we need also to mark the “activity percent complete” on technique for computing performance percent complete on earned value tabs of admin preferences?
4.Is there any way that the total performance % will roll up without assigning resources?
hoping for your response.
Has the project been baselined??
1 - Check in the WBS view Earned Value tab that you have the radio button Activity Percent Complete checked under the heading Technique for Computing Performance Percent Complete - Still cant work out why it wouldnt roll-up though - it has always worked for me
2 - Remaining duration should be a manual input base on project lead/engineer advice - not autocalculated using the tool
3 - Should fix when Step 2 is done
4 - Will be due to the fact that the remaining duration is not being changed
cheers
mr james,
thanks for responses.
by the way, all activities now are resources loaded(cost & manpower) & already changes to % complete type as(physical)but still the problems continue.
1.it doesnt roll up the total % completion of the project as you recommended to use a column for performance % complete.
2.the remaining duration doesnt change for each activity
3.doesnt show the project calculated finish due to unchange of remaining duration each activity
4.total % completion(by duration) still increasing without any progress from previous month when updating to succeeding month.
hope to hear feedback.
thanks
assign them all as physical % complete, if they are anything different at the minute it is easy to change them all using global change
Dear Mr james,
In % complete type,should i assign the activities as duration or physical in this matter?
unfortunately physical % complete doesnt roll up to a project level. if your project is fully costed then call up a column called performance % complete which should mirror physical % and this will roll up through the wbs levels to a total project percentage completion
i really appreciated your respons mr james, i would try too, but how could I see the "total project percentage completion" in terms of physical???
hope for your respons.
because if you are using duration % complete then that fact is true, try using physical % complete as it is a much more meaningful figure, i never use duration % complete