Question with OT

D
Darren Kosa 👤 Member for 18 years 4 months

Chin,



Such is life my friend, sometimes there isn’t always a suitable solution.



Regards,



Darren

D
Darren Kosa 👤 Member for 18 years 4 months

Hi Chin,



MS Project only has two rates, Standard and Overtime. Unfortunately this means that there is only one overtime rate available. It is common practice in the UK to pay two overtime rates (time and a half and double time) so I understand your frustration.



The only ways I have found to skirt round this issue are by using a dummy resources (a copy of the named resources with OVT in the description) to capture the Sun / PH overtime, or capturing Sun / PH the hours, calculating what the additional overtime cost will be and then forcing the extra costs into the schedule.



Sadly not ideal by any means.



Regards,



Darren

Forum Sponsor

Top Posters

AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts