P3 to P6

P
Paul Harris 👤 Member for 25 years 2 months

You have to manually adjust calculation options, durations, leads and lags etc until the schedules look the same.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

R
Riyadh Yahia 👤 Member for 17 years 10 months

Thanks to our respected auther for his interest in my subject,I got your Point, but how can I come over that problem????



regards



riad

P
Paul Harris 👤 Member for 25 years 2 months

When you convert a schedule from one software package to another you are doing a data conversion not schedule conversion.



All products have different algorithms and unless you are either lucky or have a very simple project schedule it is my experience that schedules will never calculate the same results in different products.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts