This information is really great, but I have a related question ...
What about Rolling up the same at WBS levels (execluding Performance % Complete which is purely connected to the WBS - but needs additional updation to the new Milestones under the WBS)?
There were two ways as in P3: 1) Duration 2) Weight (Cost or Units)
Duration Case:
Item Duration %
WBS 18d 20% = 100*(0.5*5 + 0.1*15)/20
Activity 1 5d 50%
Activity 2 15d 10%
Cost or (Weight) Case:
Item Duration Cost %
WBS 18d 1500 36.7% = 100*(0.5*1000 + 0.1*500)/1500
Activity 1 5d 1000 50%
Activity 2 15d 500 10%
These two options were simply available in P3 ...
But now in P6 it is done that way (exactly copied from the manual):
[(Summary Current Original Duration – Summary Remaining Duration) / Summary Current Original Duration] * 100
Now, please me ask my question if any one can help me ...
I dont believe that a powerfull tool was available in P3 now canceled in P6 ... Till now I only doubt my knowledge ...
So, please if anyone can help me to find out how I can automatically get the weighted progress the way described in Case 2 above as we used to apply it in P3.
Thank you very much.
Hi Friends,
Here I got it in Prief alltogether in one place:
Percent Complete Type The activity percent complete type is one of "Duration", "Units", or "Physical". The percent complete type controls whether the Activity % Complete is tied to the Duration % Complete, the Units % Complete, or the Physical % Complete for the activity. Set the percent complete type to "Duration" for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to "Physical" for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to "Units" for activities which are work effort driven, for example, providing a consulting service.
Activity Percent Complete Fields
Physical % Complete The activity physical percent complete. The physical percent complete reflects the actual progress made on the activitys work products so far. Physical percent complete can be manually entered by people familiar with the status of the activitys work products or it can be based on the completion of assigned Steps. Always in the range 0 to 100.
Duration % Complete The percent complete of the activity duration. Computed as ((Planned Duration - Remain Duration) / Planned Duration) * 100. Always in the range 0 to 100. The planned duration is taken from the current plan, not from the current baseline.
Duration % of Planned The activity actual duration percent of planned. Computed as (Actual Duration / BL Duration) * 100. The value can exceed 100. The BL Duration is the activitys at complete duration from the current baseline.
Activity % Complete The activity percent complete. This value is tied to the activity Duration % Complete, Units % Complete, or Physical % Complete, depending on the setting for the activitys Percent Complete Type, which is one of "Duration", "Units", or "Physical". Always in the range 0 to 100.
Schedule % Complete The Schedule % Complete specifies how much of the activitys baseline duration has been completed so far. Computed based on where the current data date falls between the activitys baseline start and finish dates. If the data date is earlier than the BL Start, the Schedule % Complete is 0. If the data date is later than the BL Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline.
Note: Summary Schedule percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWS* 100) / BAC, regardless of what earned value technique is selected for the activitys WBS.
Performance % Complete Performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activitys WBS. The Performance % Complete specifies what percentage of the activitys planned worth has been earned so far.
Note: Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP * 100) / BAC, regardless of what earned value technique is selected for the activitys WBS.
Best Regards
Hi Roldan,
I got your point regarding the difference % relation of activty type and %age, but I want to know the difference of the %age itself as stated in my first inquiry.
thx
Hope this can help for all...
Percent Complete Type The activity percent complete type is one of "Duration", "Units", or "Physical". The percent complete type controls whether the Activity % Complete is tied to the Duration % Complete, the Units % Complete, or the Physical % Complete for the activity. Set the percent complete type to "Duration" for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to "Physical" for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to "Units" for activities which are work effort driven, for example, providing a consulting service.
More....
Regards,
Roldan
Thank you Mark for ur help
Sorry mate,
Dont know why, but for some reason the instructions dropped out when I posted it...
They were...
Go to the View menu,
Check the Hint help
Bring up the percent complete columns & select each field that you want to know about.
Hi Riad,
The easiest way to understand the differences between the various percent complete types in Primavera is to go to the menu then check the . Then bring up your column fields & you will be able to see the differnces between the way the the various percent completes are calculated
Hope this helps
Mark