Colunms for Budgeted Units Material
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Pacificio,
In Primavera 6 the resourse types are defined as: Labor,Non labor and Material.
But when you want to add a column for the material, you donot find a column for it! the reason in my openion that P6 consider Material & Equipment as Non Labor.
So U add a Non Labor Column then modify the col. heading to material.
i hope this will do
Regards
riad
Hi Pacifico
I think the reason why you can’t find Material Units under available columns is that usually activity has more than one type of material assigned to it that’s why it can’t be summarized to activity level instead of manpower.
(for instance Form & Rebar & Pour activity will have X m3 of concrete as material and Y tonne of rebar).
The way around for one particular type of material is to create custom field and update it from resource assignments data via Excel
Regards,
Andrew
Some guy told me a way, it is a trick after all, you can define the cost of the corresponding material as 1$/unit, and you put the budget cost as a column, and revise the name of the column,
so the method is to make the column like you require, but it is the cost actually.
Pacifico
This is a request for improvement to Primavera from some major German EPC-contractors - inclusive the unit of measurement. How theyll solve, if you have multiple materials with different units, we asked Primavera for a solution. Until now not possible.
May be youll send a mail to Primavera as well.
Regards
Dieter