MS Project can track progress using % Complete (Duration) and % Work Complete (Work).
Duration is an estimate of time a task will take.
Work is an estimate of labour that will used to complete the task.
As an example, a task can be completed in 1 day using 2 resources, so using a standard 8 hour working day the Duration will be 1d or 8h but the Work will be 2d or 16h.
Why will the Work be 2d but the Duration only 1d? This is because Work has been calculated using man-days and Duration has been calculated using calendar-days.
A man-day in this example = 1 resource working 8h, but there are 2 resources working on the task who will be a cost to the project, so it will be 2 man-days.
Getting back to your problem, as there isn’t labour or material tracking in your programme, I’m not sure how you can track progress using Work.
Regards,
Darren
EDIT: I should mention that calendar day in this example means a work day, Monday / Tuesday / etc.
Need some knockings :). This is how I prepare my programme. 1.Link task. 2.Enter the contract sum in fixed cost column to produce s-curve. 3.track using percent complete 4.compare schedule progress & actual progress using number columns. I dont tract actual start. No labour and material tracking. Just lump sum contract cost. I get confuse when someone tells me to track progress using work not duration. Please assist. If need so, I would be glad to email my work.
Isnt the good ole triangle made from scope, time and cost?
Apart from the use of the word "Effort" in a setting "Effort Driven" in connection with Task Type and the realation W = E x D where E stands for "Effort", there is no such thing as Effort in MSP as some sort of quantity of something which can be expended or logged or measured or recorded, and also not outside MSP either.
MSP knows about Duration, Work and Cost and these are the only "quantities" that have an Actual and a Remaining which can be measured or recorded.
Could you please explain what you mean by work and effort? From my understanding they are pretty much one and the same.
I believe MS Project only recognises Duration (the period of time required to complete the task) and Work (the total labour required to complete the task).
They generally form two sides of the project management triumvirate, quality being the other.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Got to find some way to get to sleep at night when the alcohol doesn’t work haven’t I!!
Brad,
By talking b******s I take it you mean taking timeout to help explain to someone the theory behind the practice??
I’ll have you know I haven’t been on a single course for a least a couple of weeks, so it’s always good to keep your eye in!!
Regards,
Darren
Hi Aziz,
MS Project can track progress using % Complete (Duration) and % Work Complete (Work).
Duration is an estimate of time a task will take.
Work is an estimate of labour that will used to complete the task.
As an example, a task can be completed in 1 day using 2 resources, so using a standard 8 hour working day the Duration will be 1d or 8h but the Work will be 2d or 16h.
Why will the Work be 2d but the Duration only 1d? This is because Work has been calculated using man-days and Duration has been calculated using calendar-days.
A man-day in this example = 1 resource working 8h, but there are 2 resources working on the task who will be a cost to the project, so it will be 2 man-days.
Getting back to your problem, as there isn’t labour or material tracking in your programme, I’m not sure how you can track progress using Work.
Regards,
Darren
EDIT: I should mention that calendar day in this example means a work day, Monday / Tuesday / etc.
Hi guys,
Need some knockings :). This is how I prepare my programme. 1.Link task. 2.Enter the contract sum in fixed cost column to produce s-curve. 3.track using percent complete 4.compare schedule progress & actual progress using number columns. I dont tract actual start. No labour and material tracking. Just lump sum contract cost. I get confuse when someone tells me to track progress using work not duration. Please assist. If need so, I would be glad to email my work.
regards
aziz
Hi guys
Thank you for the messages, the question was perhap incorrect question to ask. I have now used % of work completed.
I was mixing effort with work.
Thanks again
Trevor,
It depends who you ask ;o)
I will agree with you that the concept of the triple constraint is a bit of an ironic misnomer.
Regards,
Darren
Isnt the good ole triangle made from scope, time and cost?
Apart from the use of the word "Effort" in a setting "Effort Driven" in connection with Task Type and the realation W = E x D where E stands for "Effort", there is no such thing as Effort in MSP as some sort of quantity of something which can be expended or logged or measured or recorded, and also not outside MSP either.
MSP knows about Duration, Work and Cost and these are the only "quantities" that have an Actual and a Remaining which can be measured or recorded.
Hi Emmanuel,
Could you please explain what you mean by work and effort? From my understanding they are pretty much one and the same.
I believe MS Project only recognises Duration (the period of time required to complete the task) and Work (the total labour required to complete the task).
They generally form two sides of the project management triumvirate, quality being the other.
Regards,
Darren