Leveling priorities
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi all,
How can i reduce the manpower for a specified month for an ELV project. I tried to reduce many parallel activities,but i didn't traced any massive change. please help me with your valuable suggestions.
There is built-in Activity Leveling Priority field which should be used. You can find the column under General section.
Regards,
Andrew
David,
Thanks for the input. I hope that is how priorities are set which could help us alot
Shiv,
What I have in mind would be to also look at a combination of resource leveling, float paths, critical path to determine how to spread the work and to justify the outcomes. It will get more complex if looking at more than one project/turnaround at a time since the resources come from only 1 resource pool and thsi is yet to be worked on and see the results
Mohsen,
I am also working on similar turnaround for an LNG Plant .
Allmost my entire resource are staggered in the ist 10 days of the total 40 days as all workscope are expected to start on zero date and are 7/10 day activity.
I wanted to go for Resource levelling but the priority are to be fixed if we need to use the equipment as priority or some thing else .
I am not sure how r you going to handel .
regards
Shiv
Mohsen,
If you use an existing activity code for resource levelling priorities, it will use the collating sequence you have left the activity code dictionary in.