This is not a "conflict message", just a standard warning.
The Text2 field that you are bringing into the file has a restricted data value list and if the file you are bringing it into has the same field with data in it then that data will be lost.
I tried it but it is not working, there was a conflict message "The value list data entry option is set to restrict the field to only those items in the list. This may invalidate some existing data in the "text2" field.
Open the MSP project file that will use the Resources from the Pool.
Use Tools, Organiser to select the Fields tab, and select for Resources rather than Tasks, and drop down the file list to select the Resource Pool file (which will be there if the file is open).
Then just copy the custom fields into the project file.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
This is not a "conflict message", just a standard warning.
The Text2 field that you are bringing into the file has a restricted data value list and if the file you are bringing it into has the same field with data in it then that data will be lost.
Surely all the rest worked fine?
Hi Trevor
I tried it but it is not working, there was a conflict message "The value list data entry option is set to restrict the field to only those items in the list. This may invalidate some existing data in the "text2" field.
Am I doing it wrong.
EV
Easy.
Open the Resource Pool MSP file.
Open the MSP project file that will use the Resources from the Pool.
Use Tools, Organiser to select the Fields tab, and select for Resources rather than Tasks, and drop down the file list to select the Resource Pool file (which will be there if the file is open).
Then just copy the custom fields into the project file.
Repeat similar for other files.