Hi Jorge



You do not say if you are trying to claim for extra time or money.



As always it all depends on what it says in the contract.



Usually extra work is recoverable in both time and money unless the Contractor has agreed to take on the risk.



Best regards



Mike T.

K
khawaja uddin 👤 Member for 20 years 4 months

Hi,

you can prepare your claim as a DAY WORK ,which includes the work you have done on certain dates and the eng. hr spent perform the work .

Hope it may help you .

Rgds

J
JORGE FIERRO 👤 Member for 22 years 6 months

Thanks Omer,



The question should be:



Is it possible to structure a claim for increased quiantity of engineering (more piping, concrete, cables, etc...), without changes in the scope of work ?



If yes, please an example.



Thanks,



Jorge

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts