Summarization for Custom data item-Please help
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Rante,
If you are using P6 (with Undo) and you only you need a quick what if scenario, you could add the calendar column (From General) change the first acivity to 7 day workweek then use fill down see what your finish date is compares to the original calendar.
Then Undo.
If your using P5 then make a copy which can be deleted afterwards.
Rante
Sorry I currently have no solution; just tried with a UDF.
EF-ES uses the same calendar as the activity. My idea was that it may use the base calendar.
Regards
Dieter
Thank you Dieter for your reply, but what I need is to show durations(Total Durations actually)of the whole project.
You see, P3 have a standard "Orig Dur" Column, wherein the formula that it uses is generally EF-ES.
Since I am using 3 different calendar id,it does not reflect the total calendar days but working days only on the Summary.
What I need is another column which works same as that of "Orig Dur" column but uses calendar 3 only without changing anything from the logic of the schedule.
Thank you again.
RANTE
Doha, Qatar
Rante
I assume you want to show durations of some groups of activities. May be youll use a Level of Effort or Hammock for each group and assign cal no.3 to them. In your presentation or report youll show only these LoE - by a filter.
Regards
Dieter