Have all your tasks been progressed to a status date?
Are there any Finish-Start tasks in the schedule where a task successor has a value greater than 0% Complete, but the predecessor is not 100% Complete?
If a successor is 5% Complete for example, it will have an Actual Start. This means that the start of the task has been fixed to that date and will not move (similar to a Must Start On constraint).
If the predecessor task isn’t complete and the Finish date moves past the Actual Start of its successor task, then it will show negative values in the Total Slack column. This may also account for the numbers after the decimal point.
Tasks in the Total Slack column have values that = -16d / -20d etc.
Or
Tasks in the Total Slack column have values that = 16.27d / 5.65d etc.
If it is Total Slack = -16d / -20d, have you looked at all the suggestions in post #14? If it is Total Slack = 16.27d / 5.65d, is your schedule effort driven and / or do you have split tasks?
The majority of the time, Total Slack is displayed as whole numbers (days / hours / etc.), but occasionally the Start / Finish dates of tasks don’t exactly match the default Start / End times. This is most likely the cause of your problem.
You need to check to see if this is the case
Go to Tools > Options > Calendar and make a note of the default Start / End times.
Then go Tools > Options > View and change the date format to include hh/mm.
When you look at your schedule in the Gantt View, your Start / Finish dates should look something like this… Tue 08/07/08 08:00.
All you then have to do is scroll through the tasks and look at the hh/mm part of the Start / Finish dates. When you find any times that look something like Tue 08/07/08 08:17, work your way back through the network until you find the offending task and decide what you have to do with it.
Sometimes this is caused by resource work (effort driven) increasing or decreasing the Duration value, other times because split tasks change the Duration and Start / End values by rescheduling uncompleted work to start after the status date.
thanks darren it rectified one of the task in the ddadline column had a date i made it to NA no there are no negative date ... but there is one problem some of the total slack arecoming in decimals
Insert the ‘Constraint Type’ and ‘Constraint Date’ columns. Ideally all tasks (apart from the start activity) should have a flexible constraint (As Soon As Possible or As Late As Possible).
The constraints that are probably giving you negative slack are the hard constraints (Must Start On or Must Finish On). Look down the column or use a filter to isolate these tasks and decide whether it needs a new constraint type or you need to change the constraint date.
Some Task or Tasks somewhere in the critical path have either date constraints which are earlier than their "natural starts and finishes, or deadlines which are earlier than their finishes, or both, and so all of their predecessors therefore have negative lag.
Since I cannot see how many date constraints you have or where they are, same for deadlines, I cant say which ones to fix, but the first thing I would do is remove all of them.
Both the Date Constraints and Deadlines show up in the indicators column or can be seen in the Date Constraints and Deadlines columns.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
If it is happening in MS Project, change the project start date to any.
Faisal,
Have all your tasks been progressed to a status date?
Are there any Finish-Start tasks in the schedule where a task successor has a value greater than 0% Complete, but the predecessor is not 100% Complete?
If a successor is 5% Complete for example, it will have an Actual Start. This means that the start of the task has been fixed to that date and will not move (similar to a Must Start On constraint).
If the predecessor task isn’t complete and the Finish date moves past the Actual Start of its successor task, then it will show negative values in the Total Slack column. This may also account for the numbers after the decimal point.
Regards,
Darren
One bridge at a time.
First fix neg total slack.
decimals are a different problem. Fix that next.
my dear tom dick and harry pls read read the post carefully is is coming in decimals as well
i have removed the date constraints and the deadlines also
but still it persists the predecessors are there but no negative lag
This question was answered several times, some time ago.
There are only two possible causes of negative total slack:
1) Date Constraints
2) Deadlines
Can you please confirm that you have shown the columns amended the plan so that you have none of either?
Not thought to be a direct cause compared to above, but worth checking anyway, do you have SS, SF, FF predecessor links and/or negative lag?
tasks in the total slack have negative values as well in decimal like -25.13 days/-28.13 days
Faisal,
OK I’m confused… what is the problem?
Tasks in the Total Slack column have values that = -16d / -20d etc.
Or
Tasks in the Total Slack column have values that = 16.27d / 5.65d etc.
If it is Total Slack = -16d / -20d, have you looked at all the suggestions in post #14? If it is Total Slack = 16.27d / 5.65d, is your schedule effort driven and / or do you have split tasks?
Regards,
Darren
dear darren
the negative values for total slack for critical activities still persists
Faisal,
The majority of the time, Total Slack is displayed as whole numbers (days / hours / etc.), but occasionally the Start / Finish dates of tasks don’t exactly match the default Start / End times. This is most likely the cause of your problem.
You need to check to see if this is the case
Go to Tools > Options > Calendar and make a note of the default Start / End times.
Then go Tools > Options > View and change the date format to include hh/mm.
When you look at your schedule in the Gantt View, your Start / Finish dates should look something like this… Tue 08/07/08 08:00.
All you then have to do is scroll through the tasks and look at the hh/mm part of the Start / Finish dates. When you find any times that look something like Tue 08/07/08 08:17, work your way back through the network until you find the offending task and decide what you have to do with it.
Sometimes this is caused by resource work (effort driven) increasing or decreasing the Duration value, other times because split tasks change the Duration and Start / End values by rescheduling uncompleted work to start after the status date.
Regards,
Darren
thanks darren it rectified one of the task in the ddadline column had a date i made it to NA no there are no negative date ... but there is one problem some of the total slack arecoming in decimals
Faisal,
Let me make sure I understand you correctly.
1) In the Constraint Date column ALL tasks are ‘NA’
2) In the Constraint Type column ALL tasks are ‘As Soon As Possible’
3) In the Deadline column ALL tasks are ‘NA’
Is this correct?
Also a few more questions…
1) Is your project scheduled from the project finish date? (Project > Project Information)
2) Are there any external links in your project to other projects that have hard constraints?
3) Have you added any VBA code that that uses / changes any of the Start / Finish / Duration / Constraint fields?
Regards,
Darren
yaara its total slack
total float
i have checked it nothings is wrong
i have doe it what u said but still the negative days persists it is not being removed
Hi Faisal,
Insert the ‘Constraint Type’ and ‘Constraint Date’ columns. Ideally all tasks (apart from the start activity) should have a flexible constraint (As Soon As Possible or As Late As Possible).
The constraints that are probably giving you negative slack are the hard constraints (Must Start On or Must Finish On). Look down the column or use a filter to isolate these tasks and decide whether it needs a new constraint type or you need to change the constraint date.
Regards,
Darren
its not happening
PUT "NA" IN PLACE OF DATE IN TASK INFORMATION>ADVANCED-CONSTRAINT DATE.
REGARDS
DEB
Trevor
How to remove the constraints plz say
Some Task or Tasks somewhere in the critical path have either date constraints which are earlier than their "natural starts and finishes, or deadlines which are earlier than their finishes, or both, and so all of their predecessors therefore have negative lag.
Since I cannot see how many date constraints you have or where they are, same for deadlines, I cant say which ones to fix, but the first thing I would do is remove all of them.
Both the Date Constraints and Deadlines show up in the indicators column or can be seen in the Date Constraints and Deadlines columns.