Just delete all of the resources for 2 of them (ctrl-D) from a blank cell) directly in the Resource Names column of the Entry Table. Then run/print the graph etc in Resource Graph View, then close the file, dont save, re-open and do the same for the other buildings.
Or save the Resource Names column in a spare text column so you can copy/paste to and from it so you dont have to close and re-open.
Thanks for your quick response - tried it doesnt work! the filtering obviously does, but the resources are still for the whole project and I can only view them individually not as a whole or summary no. of men. Thanks for trying though
Since you need it quick, here it is rough and not checked.
Easiest way to separate the buildings is to use a spare Text field and just fill in the field with ctrl-D (fill down) Building 1, Building 2 etc, then make a filter (Project, Filtered For etc) which reads the field.
I think that if you filter out the buildings you dont want and then go to the Resource sheet, Resource graph etc, you should get the graphs just for the building that the filter brings back. Not sure, not checked.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Say you have 3 buildings.
Just delete all of the resources for 2 of them (ctrl-D) from a blank cell) directly in the Resource Names column of the Entry Table. Then run/print the graph etc in Resource Graph View, then close the file, dont save, re-open and do the same for the other buildings.
Or save the Resource Names column in a spare text column so you can copy/paste to and from it so you dont have to close and re-open.
This might seem clumsy but should work.
Trevor
Thanks for your quick response - tried it doesnt work! the filtering obviously does, but the resources are still for the whole project and I can only view them individually not as a whole or summary no. of men. Thanks for trying though
Regards
Andrew
Since you need it quick, here it is rough and not checked.
Easiest way to separate the buildings is to use a spare Text field and just fill in the field with ctrl-D (fill down) Building 1, Building 2 etc, then make a filter (Project, Filtered For etc) which reads the field.
I think that if you filter out the buildings you dont want and then go to the Resource sheet, Resource graph etc, you should get the graphs just for the building that the filter brings back. Not sure, not checked.