what is impact on schedule using negative Lag
Forum Sponsor
Top Posters
Hashil Ali
0 posts
Nigel Hussey
1 posts
James Williams
74 posts
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
If you change the relations from FS with -ve lag to SS with +ve lag be sure to include a FF relationship between the same two items if you do not you may be finishing the successor before the predecessor completes.
Hi Salauddin,
Using negative lags in the relationship has no effect on the schedule.
you can change the relations from FS with -ve lag to SS with +ve lag.
Hope that this will help.