P3 regards MSP summary activities as "Topic activities".
Quote
It is recommended that you remove all Topic Activities by promoting ALL activities to Outline Level 1 and deleting redudant Parent Activities. You will need to check that all logic is at the lowest Outline Level before promoting activities
Unquote
(In "Project Planning Using P3 V3.1" by Paul E. Harris)
Thanks a lot, ya by data date i mean status date only.
Now i am having a new problem. i a changing a MSP schedule to a P3 one. in the MSP schedule there are summary activities , these are as well coming to the p3 schedule as activities with huge durations.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Alexandre,
Your advice is really appreciated.
regards
deb
Pranab,
it may be easier to do in P3:
1. Define the WBS structure of your project in P3
2. Make sure you define the upper level to represent the whole project and one level for each outline level in MS Project
3. Apply the WBS to the activities in P3
4. Remove all the Topic activities in P3 (run a filter saying Activty type EQ Topic to display these activities only)
Hope this helps
Alexandre
Hello Aexandre,
How to do that can you please let me know in a step by step manner.
regards
deb
Pranab,
P3 regards MSP summary activities as "Topic activities".
Quote
It is recommended that you remove all Topic Activities by promoting ALL activities to Outline Level 1 and deleting redudant Parent Activities. You will need to check that all logic is at the lowest Outline Level before promoting activities
Unquote
(In "Project Planning Using P3 V3.1" by Paul E. Harris)
Alexandre
Dear Darren,
Thanks a lot, ya by data date i mean status date only.
Now i am having a new problem. i a changing a MSP schedule to a P3 one. in the MSP schedule there are summary activities , these are as well coming to the p3 schedule as activities with huge durations.
Please help.
regards
deb
Hi Deb,
By Data Date I’m assuming you mean Status Date (the last date the project was updated).
Project > Project Information
You can also set the Project Start / Finish Dates and Current Date this way.
To set the project baseline.
Tools > Tracking > Save Baseline
Regards,
Darren