Productivity factor in P5

S
shiv rao 👤 Member for 18 years 3 months

You need to use Global Chaneg .



And select Activity Resource Assignment .



Change Budgeted units for All REsources from 1 to 1.15



regards



shiv

L
Larry Rino 👤 Member for 18 years 7 months

Sorry but you need to input the new figures (+15%) manually...



Good day