my answer to post # 1 is No.



but checking if "details are enough" is quite subjective especially if you’re dealing with engineering (design) and procurement.



I guess you can only check it generally by making sure that the whole contacted "scope of works" are covered (just to establish the baseline), but as you go further, things will be different if Design Details are coming into your hand.



I suggest to put a scoring system for schedule revisions as well.

O
Oliver Melling 👤 Member for 19 years 1 month

Like checking if it has enough detail, if the logic is any good, if it is properly resourced, if it has been optimized, if it is in line with the planning procedures etc.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts