1. Set up a formula to put a date in Start7 that represents "Start" plus "number-of-%WorkComplete-days".
Assuming a 10 work day duration, a %WorkComplete of ...
10% would calc "number-of-%WorkComplete-days" as 1 day;
20% would calc "number-of-%WorkComplete-days" as 2 days,
etc.
1a. Display the Start7 column
1b. RightMouseButton on the column header and select "Customize fields..." from the context menu popup
1c. In the Customize fields popup click on the "Formula" button
1d. In the Formula popup paste the following formula:
projdateadd([Start],(ProjDateDiff([Start],[Finish])*[% Work Complete]/100))
This will
A. take the Start date of the task
B. calculate the number of project work days [thus well ignore weekends, etc.] in minutes [Projects internal calculations are always done in minutes]
C. calculate the percent of those minutes that have elapsed based on the %WorkComplete [you could also choose %Complete]
D. Add that calculation to the Start date
E. Put the result in Start7
2. Set up the Gantt chart to display the information.
2a. View > Gantt
2b. Format > Bar Styles
2c. Locate the "Progress" row
2d. Click on the cell on that row that is underneath "To". (If it wasnt changed by someone else, it should be showing "Complete Through")
2e. Select Start7 (the field we calculated above).
Partial allocation: sheesh, were just trying to help people here. I have no way of knowing how your individual resources and team resources are going to be assigned or how you handle overtime or any of a dozen other questions.
You, after all, are the one who said an activity "is 10 days long" and theres no way anyone would interpret that as meaning that a resource (or a team of resources) is assigned 100% to that task for that duration.
But youre probably right about one thing: I guessed you had already looked around this site and found that the various equations used by others werent applicable in your case. If they were, you wouldnt have posed your question. Since you did pose your question, it seems quite reasonable to ask for clarification.
Have a nice "next life" because this one clearly isnt going well for you.
And what happens if the baseline start is the 10th and it starts on the 8th? IT SHOWS AS STARTING EARLY, THE PLANNED % IS STILL GOING TO BE 0%, THE BASELILNE BAR WILL BE TO THE RIGHT OF THE ACTUAL BAR
And what happens if the resource is allocated at 10% and the task can start late but still be finished on time (or early!)? WOULD YOU RATHER HAVE RESOURCE STOOD AROUND ON AN OFFSHORE INSTALLATION AT $$ PER DAY JUST SO YOU CAN START AN ACTIVITY WITH A FULL TEAM?? I WOULD ASK MYSELF SOME SERIOUS QUESTIONS IF I HAD AGREED A SCHEDULE WHERE TASKS CAN START LATE WITH 10% OF THE WORK FORCE AND STILL FINISH EARLY,, DO YOU HAVE TO STAND INFRONT OF PROJECT MANAGEMENT OFTEN
And how do you plan to incorporate Slack in your equation?
As I said earlier: please give us the equation you want used
DONT WORRY ABOUT YOUR HELP WITH THE PLANNED PERCENTAGE QUESTION
i want to show the data on the left hand side of the view i.e. the table, not the Gant chart side,, and what i would llike to show is the % of the Baseline that should have been achieved by the current date.
by this i mean, if an activity is 10 days long and is planned to start on the 10th,, then the baseline will show 0% if the actual date is the 9th,, however,, if the actual date (time-now) is the 15th and the activity has NOT progressed in any way then the actual % will be 0% and the planned will be 50%,,
i use this as a visual on my plans to show slippage
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
In Format, Bar Styles make a new style on a new line at the top of the list.
Give it any name like "Baseline % Planned Complete".
Select the shapes and colours for the bar and the ends of the bar.
Select for Normal Tasks.
Put it on Row 2
Make it start at Start10 and finish at Finish10.
For Milestones, make another Bar Style on the next line under the first
Give it any name like "Baseline % Planned Complete".
Select the shapes and colours for the bar, but in this case only the left hand end
Select for Milestone Tasks.
Put it on Row 2.
Make it start at Start10 and finish at Start10.
Put a formula in Start10.
[baseline start]
Put a formula in finish10:
IIf([Baseline Start]>[Status Date],[Baseline Start],IIf([Baseline Finish]<[Status Date],[Baseline Finish],[Status Date]))
Put a formula in a spare number field, Number10:
IIf([Baseline Finish]<[Status Date] Or [Baseline Finish]=[Status Date],100,IIf([Baseline Start]>[Status Date],0,IIf([Baseline Start]<[Status Date] And [Baseline Finish]>[Status Date],ProjDateDiff([Baseline Start],[Status Date])/[Baseline Duration])*100))
Put a formula in a spare text field, Text10:
[Number10] & "%"
Format the Bar Styles to put the Number10 text on the end of the bars.
1. Set up a formula to put a date in Start7 that represents "Start" plus "number-of-%WorkComplete-days".
Assuming a 10 work day duration, a %WorkComplete of ...
10% would calc "number-of-%WorkComplete-days" as 1 day;
20% would calc "number-of-%WorkComplete-days" as 2 days,
etc.
1a. Display the Start7 column
1b. RightMouseButton on the column header and select "Customize fields..." from the context menu popup
1c. In the Customize fields popup click on the "Formula" button
1d. In the Formula popup paste the following formula:
projdateadd([Start],(ProjDateDiff([Start],[Finish])*[% Work Complete]/100))
This will
A. take the Start date of the task
B. calculate the number of project work days [thus well ignore weekends, etc.] in minutes [Projects internal calculations are always done in minutes]
C. calculate the percent of those minutes that have elapsed based on the %WorkComplete [you could also choose %Complete]
D. Add that calculation to the Start date
E. Put the result in Start7
2. Set up the Gantt chart to display the information.
2a. View > Gantt
2b. Format > Bar Styles
2c. Locate the "Progress" row
2d. Click on the cell on that row that is underneath "To". (If it wasnt changed by someone else, it should be showing "Complete Through")
2e. Select Start7 (the field we calculated above).
Lewis, thank you.
How ever, what i wanted show on the gantt chart is not the text but the base line progress on the bar similar to percentage complete (Actual).
Lets assume that your calculation puts the % in the Number1 field.
View > Gantt
Format > Bar styles
In the popup:
Click on the row labelled "task"
Click on the tab labelled "text"
Click to the right of the position label(left, right, top, bottom, as appropriate) and select "Number1"
Click on OK
Can some one help me how to display that perecentage on the Gannt chart
Darren,
your a legend,, thank you very much for your help,, all works perfectly now.
many thanks and have a good weekend
Jon
Early start: ok, 0%.
Partial allocation: sheesh, were just trying to help people here. I have no way of knowing how your individual resources and team resources are going to be assigned or how you handle overtime or any of a dozen other questions.
You, after all, are the one who said an activity "is 10 days long" and theres no way anyone would interpret that as meaning that a resource (or a team of resources) is assigned 100% to that task for that duration.
But youre probably right about one thing: I guessed you had already looked around this site and found that the various equations used by others werent applicable in your case. If they were, you wouldnt have posed your question. Since you did pose your question, it seems quite reasonable to ask for clarification.
Have a nice "next life" because this one clearly isnt going well for you.
Jon,
Did you not get Niek’s formula to work?
The Custom Field, Number12 I think in his example, should display what you’re after.
Regards,
Darren
And what happens if the baseline start is the 10th and it starts on the 8th? IT SHOWS AS STARTING EARLY, THE PLANNED % IS STILL GOING TO BE 0%, THE BASELILNE BAR WILL BE TO THE RIGHT OF THE ACTUAL BAR
And what happens if the resource is allocated at 10% and the task can start late but still be finished on time (or early!)? WOULD YOU RATHER HAVE RESOURCE STOOD AROUND ON AN OFFSHORE INSTALLATION AT $$ PER DAY JUST SO YOU CAN START AN ACTIVITY WITH A FULL TEAM?? I WOULD ASK MYSELF SOME SERIOUS QUESTIONS IF I HAD AGREED A SCHEDULE WHERE TASKS CAN START LATE WITH 10% OF THE WORK FORCE AND STILL FINISH EARLY,, DO YOU HAVE TO STAND INFRONT OF PROJECT MANAGEMENT OFTEN
And how do you plan to incorporate Slack in your equation?
As I said earlier: please give us the equation you want used
DONT WORRY ABOUT YOUR HELP WITH THE PLANNED PERCENTAGE QUESTION
And what happens if the baseline start is the 10th and it starts on the 8th?
And what happens if the resource is allocated at 10% and the task can start late but still be finished on time (or early!)?
And how do you plan to incorporate Slack in your equation?
As I said earlier: please give us the equation you want used.
hello,
i want to show the data on the left hand side of the view i.e. the table, not the Gant chart side,, and what i would llike to show is the % of the Baseline that should have been achieved by the current date.
by this i mean, if an activity is 10 days long and is planned to start on the 10th,, then the baseline will show 0% if the actual date is the 9th,, however,, if the actual date (time-now) is the 15th and the activity has NOT progressed in any way then the actual % will be 0% and the planned will be 50%,,
i use this as a visual on my plans to show slippage
many thanks
1. Do you mean in the lefthand side of the display (the grid) or the righthand side of the display (the Gantt chart)?
2. Please give us the equation using the field names like "Baseline start", "Actual Start", etc.