How do we know What is the Proj. % Comp ? IN P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Alex,
Its not shortcutting. Our company doesnt want to put the costing for resource. And also they do give the % complete on basis of physical justification.
Suresh
Yep the prolem is how the scheduler/planner do not want to do his/her job properly.
There is no short cut in life, resource load your schedule and either use cost or resource unit to calculate your % complete
Good Luck
ALex