The sum total is approx 6,000 lines now. Versions are saved to separate folders weekly, monthly when reports are due.
Only two others have rights to access the folders, hard copies are available to anyone the correct clearance.
Im using unique IDs. If I copy the projects out of the master schedule, excluding the summary task (MSP 2003) I can create a single schedule, BUT where a link was to another project the schedule decides that it would be better to move the task to either above or below the linked task of the pasted sections ie out of the area/group where it came from rather than staying where it was originally. Otherwise this would be acceptable. Im still working on it ........ Ill get there sometime.
Where you have created several smallish plans, linked them and now want to create one plan. First consider the total size because if the total of the inserted plans is too large MSProject might fall over. It would be better to keep the plans individual but to move them to a folder that only you and one or two other experience planners have access to. Often safer to zip up the set of plans first. I let my project managers have copies of their own plans and only put them back into the set if they have not corrupted them. I always take a copy of the unique id in each individual plan into a number column so that I can refer back to it from the shell or master plan.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Denise
The sum total is approx 6,000 lines now. Versions are saved to separate folders weekly, monthly when reports are due.
Only two others have rights to access the folders, hard copies are available to anyone the correct clearance.
Im using unique IDs. If I copy the projects out of the master schedule, excluding the summary task (MSP 2003) I can create a single schedule, BUT where a link was to another project the schedule decides that it would be better to move the task to either above or below the linked task of the pasted sections ie out of the area/group where it came from rather than staying where it was originally. Otherwise this would be acceptable. Im still working on it ........ Ill get there sometime.
Brian
Brian
Where you have created several smallish plans, linked them and now want to create one plan. First consider the total size because if the total of the inserted plans is too large MSProject might fall over. It would be better to keep the plans individual but to move them to a folder that only you and one or two other experience planners have access to. Often safer to zip up the set of plans first. I let my project managers have copies of their own plans and only put them back into the set if they have not corrupted them. I always take a copy of the unique id in each individual plan into a number column so that I can refer back to it from the shell or master plan.
Paul
Thanks for your help.
I was thinking much the same, create a unique ID for each task across all projects in the master project (for info later).
Copy the master project to excel to save the logic information.
Remove external links in the individual projects.
Paste the projects one by one into a new project with no links between them, then use the IDs saved from excel as a guide to re-link the tasks.
The resources and calendars should be ok.
Pretty messy and labour intensive, but not to many other options.
Brian
I do not think you will be able to do this without loosing you inter project links.
If I were doing this process I would make sure all calendars and resources of each project are either identical or unique.
I would then create a new project to copy and paste each project into and then re-establish the links.
Paul E Harris
Eastwood Harris Pty Ltd
Planning and Scheduling Book Publishers
www.eh.com.au