here is the link for the latest sdks
activity6x.xls , dictionary6v7.xls , wbs.xls , project.xls
http://www.eh.com.au/software.html
Regards
here is the link for the latest sdks
activity6x.xls , dictionary6v7.xls , wbs.xls , project.xls
http://www.eh.com.au/software.html
Regards
you need Dictionary?.XLS from the Primavera Knowledge base. Loads any codes except wbs. you need P3 for that
Marshall
Thats is one of many ways to importing code to the system.
Using SDK, API, Import/Export, Third Party integration tools are just few other ways to do what is original ask for.
Each solution of course is different, in terms of time / effort / cost.
HTH
Alex
I think that the only way to do what you are asking is to add the codes to the P3 dictionary, create a dummy job using one of those codes, and then import the P3 job into P6. All of the codes will be there (might need to be re-arranged). I have done this once before (I think...). Someone else please correct me if this is not right.
Try the SDKU60 , refer to prim10191.