Planned Strat / Early Start

D
Darren Kosa 👤 Member for 18 years 4 months

Hi Shahzad,



By Planned Start, I assume you mean the dates in the ’Start’ column relating to the scheduled dates the tasks are due / planned to begin?



These dates are determined by MS Project based on a combination of calendar (project or task), precedence (task dependencies) or constraints (ASAP etc).



The Early Start date are determined by backward and forward passes (ES / EF / LS / LF), taking into account Float (Slack in MS Project). Depending on whether the project is scheduled from the Start Date or a known Finish Date (most are scheduled from the Start Date) the Early Start will be the same as the Planned / Scheduled Start.



When updating / progressing a schedule you can also use Actual Start, but that’s another story for another time...



Regards,



Darren

Forum Sponsor

Top Posters

AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts