In the past I have used a Date Range filter (or an adaptation) to achieve this. However, this shows the filtered tasks with their complete durations, regardless of the fact only a portion of the task happens during the timeframe specified in the Date Range filter.
For a quick view this is sometimes all you need, but you can also use the timescale option when printing to narrow down the field of view, so it just prints the two week window.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello,
Therre is a formulas for showwing the name of sucessor or predecessor filed in Ms-project spreedsheat.
Regards
FARES
Insert/show the Date1 field.
Right-Click on the heading of the Date1 column.
Click Customise Fields on the menu.
First Rename the Date1 field.
Call it "S Date" or similar, but you cant use "Status Date" because that is a reserved name.
Then write the formula which just consists of one function, which is the Status Date.
You can just type it or get it from the list of functions with the function button.
[Status Date] is the last one under Project, Date.
Thanks Trevor,
could you please elaborate on this
"Use a spare Date field, Date1, to store the Status Date.
Tools, Customise Fields, then Formula and Status Date is in Function,Project."
is it Function===>Project===>ProjDateValue(expression)?
Im not getting it right.
Cheers
Say we want the look-ahead to be 3 weeks ahead of the Status Date.
You can do the same thing similar for the Current Date.
Use a spare Date field, Date1, to store the Status Date.
Tools, Customise Fields, then Formula and Status Date is in Function,
Project.
Use another spare Date field, Date2, to store the [Status Date] +21
Once you have the boundaries of your date range stored in fields you can
make a Filter which is similar to the built-in Date Range Filter but which
gets its data from the fields instead of user input.
Make a Filter called "AA 3 Week Look-ahead".
Project, Filtered For, More Filters, New.
Filter like this:
Tasks whose Start is less than or equal to [Status Date] +21
And
Tasks whose Finish is greater than or equal to [Status Date]
Hi Alex,
In the past I have used a Date Range filter (or an adaptation) to achieve this. However, this shows the filtered tasks with their complete durations, regardless of the fact only a portion of the task happens during the timeframe specified in the Date Range filter.
For a quick view this is sometimes all you need, but you can also use the timescale option when printing to narrow down the field of view, so it just prints the two week window.
Regards,
Darren
as far as I know, there is no "Data Date Line" in MSP (i dont know the latest versions)