If you create 3 Customzed Fields (Units [Number 1], Units/Hr [Number 2], Hrs [Number 3]), you can copy and "paste special link" the Hrs field to the Work field.
Note:
Tasks must be Fixed Duration.
Customized field "Hrs" must be assigned a Custom formula attribute. In my case, "Units/Units/Hr".
It's a hack at best, and not very robust, but I hope it helps.
I too feel that attempting formula based calculations might not be feasible with MS project alone. I presume MS Access could be used as the data storage(Production rates)& then can be suitably imported to MSP. What I wished was for an in-built calculation mode within MSP facilitating a drop down menu or a tab & listing the tasks and subtasks accordingly. That would mean quite a big library of combinations of tasks.
Meanwhile, I would try as per Darrens suggestion.
It’s not something that MS Project handles well, if at all, to be perfectly honest. I know Hard Dollar have a module called BID*BUILD that integrates with MS Project and which might help (but it might be an additional cost that you do not want to support).
Other than that it may be a case of playing around with the Unit % and a combination of Fixed Units / Effort Driven task type.
Let me know how you get on and if you find a solution. It would be good to know for future reference.
It is not possible in MSP because resource assignments in MSP have no special features (like production rates, or unit cost) - they are just intersections of resources and activities. You shall try to calculate activity durations basing on production rates using other software and then export calculated durations into MS Project. Maybe MS Access can do this. I did not try, because in Spider Project which I use these calculations are standard and production rates databases can be created (or imported) in the program.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
If you create 3 Customzed Fields (Units [Number 1], Units/Hr [Number 2], Hrs [Number 3]), you can copy and "paste special link" the Hrs field to the Work field.
Note:
Tasks must be Fixed Duration.
Customized field "Hrs" must be assigned a Custom formula attribute. In my case, "Units/Units/Hr".
It's a hack at best, and not very robust, but I hope it helps.
Thanks Vladimir & Darren,
I too feel that attempting formula based calculations might not be feasible with MS project alone. I presume MS Access could be used as the data storage(Production rates)& then can be suitably imported to MSP. What I wished was for an in-built calculation mode within MSP facilitating a drop down menu or a tab & listing the tasks and subtasks accordingly. That would mean quite a big library of combinations of tasks.
Meanwhile, I would try as per Darrens suggestion.
Kind regards,
Rubas
Hi Rubas,
It’s not something that MS Project handles well, if at all, to be perfectly honest. I know Hard Dollar have a module called BID*BUILD that integrates with MS Project and which might help (but it might be an additional cost that you do not want to support).
Other than that it may be a case of playing around with the Unit % and a combination of Fixed Units / Effort Driven task type.
Let me know how you get on and if you find a solution. It would be good to know for future reference.
Regards,
Darren
It is not possible in MSP because resource assignments in MSP have no special features (like production rates, or unit cost) - they are just intersections of resources and activities. You shall try to calculate activity durations basing on production rates using other software and then export calculated durations into MS Project. Maybe MS Access can do this. I did not try, because in Spider Project which I use these calculations are standard and production rates databases can be created (or imported) in the program.
Regards,
Vladimir