Thanks but all my option settings are correct & problem is only with few tasks other tasks are OK.If I correct it physically in resource view it changes % complete in Tracking Gantt view & doesnt spread the resource as per work happened in due corse of time.(Resources are entered in sqm of qty & no of man days- entered as material).
Yes all my tasks are resource loaded & the problem is for few tasks only.For example in one particular task my % complete (& % work complete) is entered as 18% but in resource view its 0%.So no actual work data is appearing in time scaled result of resource view (which I have to update physically in seperate spreadsheet).
Thanks for yr message but may be I didnt explain the problem properly. There are many tasks in my schedule which has been updated by me. Now for few tasks even after enetring % work complete (& % complete) in Tracking Gant view % complete is not appearing in Resource usage view.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
ya i have sent the file.
Thanks
Could you send a bit of your project with some "good" and "bad" tasks?
[email protected]
Hope this will help
Ya Alexandre
Its randomly distributed & not of a common crieteria. My proj is about 1100 Task of which about 15 Tasks resource usage results are wrong.
Can you explain what these "few tasks" are? Are they randomly distributed within the project, or is it possible to define a common criteria?
Dear Alexandre
Thanks but all my option settings are correct & problem is only with few tasks other tasks are OK.If I correct it physically in resource view it changes % complete in Tracking Gantt view & doesnt spread the resource as per work happened in due corse of time.(Resources are entered in sqm of qty & no of man days- entered as material).
You should check:
Tools, Options, Calculation, then 1st line under "Calculation Options for [Project name]"
Is the checkbox ticked or unticked? If unticked, MS Project will not update the resource actual work when you update the actual duration
Alexandre
Yes all my tasks are resource loaded & the problem is for few tasks only.For example in one particular task my % complete (& % work complete) is entered as 18% but in resource view its 0%.So no actual work data is appearing in time scaled result of resource view (which I have to update physically in seperate spreadsheet).
Do you have resources allocated to THESE tasks?
Alexandre
Thanks for yr message but may be I didnt explain the problem properly. There are many tasks in my schedule which has been updated by me. Now for few tasks even after enetring % work complete (& % complete) in Tracking Gant view % complete is not appearing in Resource usage view.
You may be confusing %Complete with %WorkComplete.
%Complete reflects the Percentage of elapsed time; %WorkComplete represents the work done.
Consider a task that has 2 days of work and 10 days of duration. After 5 days, no work has been done.
%Complete = 50%; %WorkComplete = 0%