Retainage / Retention costs in P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Yeah thiss a good idea
Thanks for the replies! I really appreciate your help.
There is no problem in P6 in having an activity "Finished" i.e. having a finish date, AND still having a remaining cost.
So I would use resources.
In addition, resources can be placed beyond the finish date of the activity, so it is possible to have, say, 10% of the resource cost happening 60 days after the end of the activity.
Have Fun!!!
Hi.
I did not check in P6 yet but Im sure you can do it if you have Primavera Contract Manager, an seperate module which can be linked to P6.