If you walk through the import you see a window "Update Project Options". Select "Advanced" in the bottom of this window. Then try "units as hours".
Sorry, one of your sentences I dont understand: "... in p3 is 4 duration is 10 days". What do you mean by this 4 = 10 ???
Regards
Dieter
Diater,
The units are same in p3 and p6. What i found is.. Unit per time in p3 is getting wrongly calculated in the p6
Eg: 8hrs per day calender
unit per day is specified in p3 is 4 duration is 10 days
In p6 it converts like this
4*10=40*8 = 800h i dont knnow how its come.. but i think this is the funda... bullshit p6..
Cheers
Suresh
Just two ideas:
1. Parameter Planning Units: Hours or Days: May be you selected days but planned in hours.
2. Resource curves: Sometimes not really compatible - e.g. "curve A" bell shaped in P3, triangle in P6.
May be others have more ideas.
Regards
Dieter