Hi,
After further exploration, I realised that even if I use “rate source” as “override”, when I move the bar, the budgeted cost automatically switches to the formula “budgeted cost=original duration x unit / price”. Only after I uncheck the “Calculate costs from units” under “resources”, can I assign budgeted cost to an activity without being affected by the movement of the bar.
Also, I can go to “Project > Resource Assignment” to get early and late cost distribution. This is good enough for me to copy the data to Excel.
Thanks.
Johnny
Dieter,
Thanks a lot. It works when I choose the “rate source” as “override” under "resource" of the activity detail.
But for late dates, there is no figure to show the cost distribution, only the graph. I still need to explore the report part to find both early and late dates cost load distribution so that I can export to Excell for S curve presentation.
Thanks and regard.
Johnny
Johnny
View Activities, detail tab resources you can ad columns. Moe mouse into that area --> right click --> columns. In the category general you can find "rate source". To learn the meaning of a data item switch on "hint help", e.g. view --> hint help.
In genera Primavera takes the budgeted costs from a resource rate. Here you can indicate to use the budgeted price you entered.
Hope this helps
Dieter
Dieter,
Can you please elaborate it?
Thanks.
Johnny
Johnny
Did you check for "Rate source"="override" together with the resource usage profile or -spreadsheet?
Regards
Dieter