I appreciate. Just like Early start and Actual start in Primavera, I was mistaken the planned start date to the Baseline start. Like I said not use to MSP.
"trying to update progress in MS project by filling the actual start column, but it changes the planned start date to the actual start date and the whole schedule."
Why is this a problem rather than completely logical?
A Task can either have a planned start date or an actual date, but not both, or different. If a task has an actual start date, this supersedes any planned start date, so the planned start date takes the value of the actual start date.
Also, it pays to remember that the left hand end of the bar of the task does not even represent the "planned" start date, but only the earliest possible start date.
You can more or less safely intend or plan to start anytime after that up to the latest possible start date, ie within the float. I only mention this because it seems to be a common misinterpretation that the early start is always the "planned" or "intended" or "scheduled" or even "promised" start date. Of course, it is best, if possible, to do tasks as soon as possible, even if they have a lot of float (dont put off to tomorrow what you can do today), but the whole point of the critical path method is to know which tasks you can relax about and which which are serious time-wise.
MSP is a completely different animal to Primavera products.
MPS essentially ignores the data date and schedules the end date of an inprogress activity from the actual start + the duration and ignores the % Complete and remaining Duration which is always linked to the % Complete.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Got the message guys.
I appreciate. Just like Early start and Actual start in Primavera, I was mistaken the planned start date to the Baseline start. Like I said not use to MSP.
Cheers all
Kunle
"trying to update progress in MS project by filling the actual start column, but it changes the planned start date to the actual start date and the whole schedule."
Why is this a problem rather than completely logical?
A Task can either have a planned start date or an actual date, but not both, or different. If a task has an actual start date, this supersedes any planned start date, so the planned start date takes the value of the actual start date.
Also, it pays to remember that the left hand end of the bar of the task does not even represent the "planned" start date, but only the earliest possible start date.
You can more or less safely intend or plan to start anytime after that up to the latest possible start date, ie within the float. I only mention this because it seems to be a common misinterpretation that the early start is always the "planned" or "intended" or "scheduled" or even "promised" start date. Of course, it is best, if possible, to do tasks as soon as possible, even if they have a lot of float (dont put off to tomorrow what you can do today), but the whole point of the critical path method is to know which tasks you can relax about and which which are serious time-wise.
MSP is a completely different animal to Primavera products.
MPS essentially ignores the data date and schedules the end date of an inprogress activity from the actual start + the duration and ignores the % Complete and remaining Duration which is always linked to the % Complete.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au