Budgeted units = actual units
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Naveen
Open "Tools" --> "Global Change" --> "New" --> select "Activity Resource Assignments" --> Give a name to this global change --> lines as indicated.
I have the impression that you are not familiar with the Global Ghange, so after you will have selected "New" youll select "Help" first. The description is very good.
If youll have any difficulties, write a private message.
Good luck
Dieter
Dieter,
I cannot put actual finish NOT EQUAL TO because I mentioned earlier that these activities have actual finish dates but the resource units have not been updated (For example if the budgeted units were 100 then actual units are left as 0). Only start & finish has been updated & this is causing the unit % complete at summary level to be very low. I tested this on a small project with 5 activities & the result has been the same.
Alex,
Its in normal gantt chart veiw.
Regards
Naveen
Hi
When you mentioned summary level, do you mean @ tracking view and project view. If it is, then its simple, you need to run project summarisation to update these details to the project level.
HTH
Alex
Naveen
Sorry, my mistake:
If actual finish NOT EQUAL
Actual this period labor units = Budgeted labor units
Regards
Dieter
Naveen
please explain what is working, and where are different result to your expectations.
Explain your steps please.
Regards
Dieter
Thanks Dieter.. but its not working..
Naveen
Global change is the right idea:
- Group ("Activity Resource Assignments")
- If actual finish >
- Actual this period labor units = Budgeted regular labor units
Please check the list before commitment. No warranty, I dont belong to Primavera - just a user
Hope this will help
Dieter