Data Value in Resource Histogram in P6

K
K D 👤 Member for 18 years 8 months

Hi.

P6 does not support this feature.

You can do it in Primavera chart module. It’s sold seperately.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Ahmed,



You cannot display or show the Data Value in the Resource Histogram. If you wish to know the Value just double click on the Histogram and it will give you the Budgeted, Actual & Remaining Value.



Thanks..





Arnold

A
Ahmed Saudagar 👤 Member for 20 years 4 months

Hi K D



In P3, when you go to Tools-Grapic Reports-Resource &Cost and select to open any report and open Contents TAB, at the bottom in the center you will find under Histogram DISPLAY DATA VALUES option. This option when checked will provide a data figure/value on top of the histogram week/month when printed.



I want to know where I can find this option in P6.



I get the resource histogram but am not able to find it.



Hope this better explains to the problem.

K
K D 👤 Member for 18 years 8 months

Hi Ahmed.

Could you elaborate your query ? We can not get it so far.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts