Hi.
In P6 you have function called "Create Reflection".
Using this function it will create a copy project and change status to "what-if". The resource in what-if project will not be calculated when you analyzing resource.
You can make changes to what-if project to get the best solution in resolving a problem. Then merge it back to original project.
regards
Hi Ken,
You could imagine temporarily change the status of a project from "Active" to "What if" if you want to consolidate without this part => Schedule Options allowed to take or not the relationship from & to other active projects. If you want to exclude only a single project of your consolidation, it could be a way.
Kindest regards.
Patricia