1. I did not understand how to simulate payments for quantities by using non-labor resources.
Lets suppose that some worker was assigned to several jobs and will be paid $20 per one meter on the first activity and $5 per kg on the second job. I want to be able to have a report on each project resource planned and actual cost.
2. Is it true that setting multiple price/unit I will be able to receive reports on each component - total cost and totals for salaries, indirect costs, etc.?
3. Project planning among other things means creating project schedule that is adjusted to existing constraints. Usual constraints include resource constraints, financial constraints and supply constraints. It is nice to know the impact of delays with supplies and financing. Unfortunately financial software does not schedule, so PM packages shall do it.
4. Using several cost estimates in parallel we can analyze project performance from many points of view. We can estimate if we will meet internal targets, if management reserves are sufficient, if we will have profit from current contract, etc. It is useful.
Best Regards,
Vladimir
Member for
18 years 6 months
Member for18 years6 months
Submitted by Oliver Melling on Tue, 2008-04-29 09:42
Tounge in cheek comment - if you really want to use your software for financial information then swap from Primavera to Asta PowerProject!!!!!!!! Alot more user friendly in this respect, actually in most others as well.
Member for
18 years 6 months
Member for18 years6 months
Submitted by Oliver Melling on Tue, 2008-04-29 09:13
to simulate that resource is paid for the quantities that had been done, not for hours that were spent
This is done by using non-labour resources.
to assign resource hour cost that consists of the salary, indirect costs, taxes and other components
Multiple Price/unit settings can be set for each resource, first could be base rate, base rate+locol overheads, + corporate overheads and so on...
to simulate project financing and to use cost constraints in project scheduling
Cashflow can be predicted via baseline cost profiles and earned value/actual costs per month can also be captured.
IMHO planning software isnt financial software, it just uses monetary values to comply with earned value management and isnt mature enough to be all things to all men.
(i.e Primavera rounding errors make it unsuitable for use as a financial tool.)
The original cost estimate should be able to provide activity budgets based upon the different rates for internal external activity.
What would the benefit of cost profiles at different rates? They are used mainly to give confidence to control the project and to also ensure the customer that you can deliver.
Member for
24 years 9 monthsRE: Cost (schedule) simulation capabilities of PM software
Hi Oliver!
Thank you for your answer.
Not everything is clear.
1. I did not understand how to simulate payments for quantities by using non-labor resources.
Lets suppose that some worker was assigned to several jobs and will be paid $20 per one meter on the first activity and $5 per kg on the second job. I want to be able to have a report on each project resource planned and actual cost.
2. Is it true that setting multiple price/unit I will be able to receive reports on each component - total cost and totals for salaries, indirect costs, etc.?
3. Project planning among other things means creating project schedule that is adjusted to existing constraints. Usual constraints include resource constraints, financial constraints and supply constraints. It is nice to know the impact of delays with supplies and financing. Unfortunately financial software does not schedule, so PM packages shall do it.
4. Using several cost estimates in parallel we can analyze project performance from many points of view. We can estimate if we will meet internal targets, if management reserves are sufficient, if we will have profit from current contract, etc. It is useful.
Best Regards,
Vladimir
Member for
18 years 6 monthsRE: Cost (schedule) simulation capabilities of PM software
Good idea, only nobody uses Powerproject!
Member for
20 years 10 monthsRE: Cost (schedule) simulation capabilities of PM software
Oliver / Vladimir,
Tounge in cheek comment - if you really want to use your software for financial information then swap from Primavera to Asta PowerProject!!!!!!!! Alot more user friendly in this respect, actually in most others as well.
Member for
18 years 6 monthsRE: Cost (schedule) simulation capabilities of PM software
Vlad,
to simulate that resource is paid for the quantities that had been done, not for hours that were spent
This is done by using non-labour resources.
to assign resource hour cost that consists of the salary, indirect costs, taxes and other components
Multiple Price/unit settings can be set for each resource, first could be base rate, base rate+locol overheads, + corporate overheads and so on...
to simulate project financing and to use cost constraints in project scheduling
Cashflow can be predicted via baseline cost profiles and earned value/actual costs per month can also be captured.
IMHO planning software isnt financial software, it just uses monetary values to comply with earned value management and isnt mature enough to be all things to all men.
(i.e Primavera rounding errors make it unsuitable for use as a financial tool.)
to use parallel cost estimates (internal cost components, contract cost components, ...), etc.
The original cost estimate should be able to provide activity budgets based upon the different rates for internal external activity.
What would the benefit of cost profiles at different rates? They are used mainly to give confidence to control the project and to also ensure the customer that you can deliver.
Regards,
Ol