DIFFERENT HOURS PER TIME PERIOD IN P5

S
Suresh Sankarankutty PMP 👤 Member for 19 years 10 months

Hi all,

Thanks for the hint and advise. I could successfully manage the problem and out of fear now. The pbm i found was we can keep the standard hrs of 8hrs in the admn preference and check on allow users to specify the number of work hours for each time period and change the required hrs per time period in user preference.



Cheers

Suresh

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Suresh

This % is always misleading for beginners. A good explanation you’ll find under Help.

Edit --> User Preferences --> Time Units --> "Help Button" --> then read, especially under hours per time period.

The basis for calculation of unit of measure always is under Admin Preferences or within the User Preferences.

If your Resource has a 10h-shift, this is 125%.

While using different calendars you’ll better display hours instead of %.



Hi Sarah

the Global default calendar is used for the summary bars, and by default will be assigned to new projects and resources.



It’s reliable to use different calendars in P6 but not easy to understand. You’ll better test it first on your test database with a test project and some test resources. Play with different calendars for activities and resources and different units per time under the preferences and you’ll get a feeling.



Good luck!

Dieter

S
Sarah Benjamin 👤 Member for 18 years 1 month

have you checked on the global default calendar? i believe that is what primavera uses to calculate the duration, so be sure to check that setting.



Enterprise > Calendars > Global radio button on top > look at what is checked off... see about the working hrs/day in that calendar. change if necessary.

S
Suresh Sankarankutty PMP 👤 Member for 19 years 10 months

Hi All,

Well, I am using P5. I am using Budgeted Units as Hours and Duration as Days. If we use unit and duration as hours there wont be any prbs. I have 10hrs global calender for activity and resource. I was trying to put 60hrs budgeted unit for a duration of 8 days. Infact, When i use 10hrs calender with a 10hrs resource calender with max/unit of 100% it would show 10*8 = 80hrs. But here i am using 60hrs as the budgeted units so that it should give me



Budgeted units Duration Max. Unit /Time

60 hrs 08 Days 75%



I want to use 75% of the resource only to this activity for a duration of 08 Days. But while entering the budgeted hrs and maximum .unit /time as 75% P5 is giving 10 Days duration eventhough i have a 10hrs activity calender. Ok here we have set up the 10hrs through the admin perference and solved the problem. But what about if i want to work in another project which is having 08hrs activity calender ???

A
Andrew Dick 👤 Member for 19 years 4 months

Suresh,

As Dieter has pointed out there are some threads on PP that discuss this already;



I have taken the liberty of adding the links below; they are essentially in order of creation.



Enjoy



Andy





1. Admin Preference Workhours Carried To All Projects





http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=43523



2. Calculation Of Activity Duration ???????????????







http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=43107





3. Confirmation Or Debunking Of My Findings







http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=43697





I couldn’t get the links to work so I pasted the links in the post, just copy and paste them if the hyperlinks don’t work for you.

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Suresh

There were some more threads on this item already. Reason is the design of P5/P6: Everything is done by hours. The calculation between hours, days, weeks, and months is done according to the parameters within the admin preferences. Not according to project’s or activity’s calendar - by the way which should be used? So either enter duration hours or, for longer activities, use expected finish date --> let P5 calculate --> delete expected finish.

Hope this will help.

Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts