Not necessary. Just display the Indicators column as you were advised. Alternately, display the "Constraint Type" column -- if it contains anything other than "As Soon As Possible" then you have constraints on the task.
One other remote possibility is that the PM is playing with you (like telling new campers to go on a snipe hunt) and has given you a schedule that has been set up to schedule from the Project Finish date. (Project > Project Information and check the Schedule From date.)
I have not entered any percentages this programme has prepared by one of our PM so I dont know the way he entered the data this is small programme having 15 activities i can send you the progrmme if you can send me the mail address
If you simply entered Start and/or Finish dates (a serious "no-no") then those tasks are constrained and will not move. Look to see if there is a little calendar in the Indicators column. If the calendar is there then youll have to double-click on the task, select the Advanced tab and change the constraint type to As Soon As Possible.
If you have entered Actuals (by changing the %Complete or by entered actual values for a task) then, again, those tasks are constrained and will not move.
There should be no reason other than Date Constraints which will prevent you from moving the whole project into the past or into the future just by changing the Start Date in Project, Project Information.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
update project in tracking tool
Not necessary. Just display the Indicators column as you were advised. Alternately, display the "Constraint Type" column -- if it contains anything other than "As Soon As Possible" then you have constraints on the task.
One other remote possibility is that the PM is playing with you (like telling new campers to go on a snipe hunt) and has given you a schedule that has been set up to schedule from the Project Finish date. (Project > Project Information and check the Schedule From date.)
Dear All
I have not entered any percentages this programme has prepared by one of our PM so I dont know the way he entered the data this is small programme having 15 activities i can send you the progrmme if you can send me the mail address
GA
If you simply entered Start and/or Finish dates (a serious "no-no") then those tasks are constrained and will not move. Look to see if there is a little calendar in the Indicators column. If the calendar is there then youll have to double-click on the task, select the Advanced tab and change the constraint type to As Soon As Possible.
If you have entered Actuals (by changing the %Complete or by entered actual values for a task) then, again, those tasks are constrained and will not move.
There should be no reason other than Date Constraints which will prevent you from moving the whole project into the past or into the future just by changing the Start Date in Project, Project Information.
Do you have Date Constraints?