Hi Colleaques



This topic is very interesting and call for care from the Contractors. i agreed with Mike that Engineers Approval does not absolve the Contractor of the consequences of incorrect setting out levels.



It is worthy to note in FIDIC (1992 Edition) red book Clause 17.1 (a &b) that it is Contractor’s responsibility the accuracy of setting out of the Works



You may read further of the last paragraph o this Clause that the checking of any setting-out or of any line by the Engineer shall not in any way relieve the Contractor of his obligations for the accuracy under the contract.



Cheers guy


M
Mike Testro 👤 Member for 20 years 5 months

Hi Abhijit



Usually the contractor is responsible for setting out his works.



Unless there are express terms in the contract the engineers approval does not absolve the contractor of the consquences of incorrect levels.



He must fix the problem quickly or he will be blamed for the delays.



Best regards



Mike Testro

A
Abhijit Kale 👤 Member for 18 years 10 months

Is it EPC contract?

If yes then fault of contractor.



Contractor have to bear expenses.



If design and drawings are supplied by the client then contracto can go for extension of time/ if thr is cluase for claims, then for claims as well.



cheers,

Abhi

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts