Double click the highest level task summary. The SUMMARY TASK INFORMATION menu will appear. Go to ADVANCE and fill up the DEADLINE box with your deadline date. The deadline date is supposed to be your preferred baseline finish.
Then, CALCULATE. (Even if the calculation option was previously set to automatic, it will not calculate automatically on this input, I dont know why...?)
Go to TOOLS, OPTION, CALCULATION and hit CALCULATE NOW.
This should show a slack on your Total Slack column of your highest task summary. Probably a negative slack if you have slippage.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Thomas,
You can try this...
Double click the highest level task summary. The SUMMARY TASK INFORMATION menu will appear. Go to ADVANCE and fill up the DEADLINE box with your deadline date. The deadline date is supposed to be your preferred baseline finish.
Then, CALCULATE. (Even if the calculation option was previously set to automatic, it will not calculate automatically on this input, I dont know why...?)
Go to TOOLS, OPTION, CALCULATION and hit CALCULATE NOW.
This should show a slack on your Total Slack column of your highest task summary. Probably a negative slack if you have slippage.
Hope this helps....
Gerry
Cannot, still the same. the negative float is not appeared in the summary bar even I put deadline in the summary bar
Hello Thomas,
Put the deadline date on the highest level summary instead. This will show your slack.
Gerry
Hello Thomas,
Put the deadline date on the highest level summary instead. This will show your your slack.
Gerry